Most stair-related permit failures come down to a handful of numbers. Learn these, and laying out a safe, comfortable stair becomes simple arithmetic.
Most US jurisdictions build on the International Residential Code (IRC). Section R311.7 sets the core stair dimensions. Your local version may differ, so always confirm with your building department.
| Rule | IRC requirement |
|---|---|
| Riser height | 7¾ in maximum |
| Tread depth | 10 in minimum |
| Variation within a flight | ⅜ in maximum (risers and treads) |
| Headroom | 6 ft 8 in minimum |
| Clear width | 36 in minimum |
| Handrail | Required on at least one side for 4 or more risers |
Example: a 108 in rise ÷ 7.75 = 13.9, so 14 risers of 7.71 in. That gives 13 treads; at 10½ in each, the total run is 136½ in (about 11 ft 4 in), and the stringer is about 14½ ft long.
A stair at the limits — 7¾ in risers and 10 in treads — is steep. Many builders aim for something closer to a 7 in rise and an 11 in tread. A traditional check is that two risers plus one tread should land around 24–25 inches.
Your brain sets its stride from the first few steps. A step that is noticeably taller or shorter is a trip hazard, which is why the code limits variation to ⅜ in within a flight. The usual culprit is the top or bottom step after flooring is added — plan for finished thickness from the start.
Exterior stairs follow the same dimensional rules. For poured steps, our concrete steps calculator estimates the concrete, including the landing; for deck stairs, the stringer length from the stair calculator tells you what lumber to buy.
This guide summarizes common IRC requirements. Your local code, as adopted and amended by your jurisdiction, is the rule you will be inspected against.
Beyond risers and treads, the IRC includes several details that inspectors check. Confirm the exact wording in the edition your area has adopted:
Say your deck surface sits 40 inches above a concrete landing pad. 40 ÷ 7.75 = 5.16, so you need 6 risers of 6.67 inches and 5 treads. With 11 in treads, the total run is 55 inches. That 55 inches of horizontal space, plus a 36 in landing at the bottom, is the footprint you need to plan for before you build.
Measure every riser and tread with a tape and write them down. If the tallest and shortest differ by more than ⅜ inch, fix it now. Check the handrail height at several points and confirm the headroom along the full length of the stair, not just at the top.
Under the IRC, 7¾ inches per riser for residential stairs. Commercial stairs under the IBC are stricter, typically 7 inches.
10 inches under the IRC, measured from the front edge of one tread to the front edge of the next.
Yes. Deck stairs are stairs, and the same riser, tread, handrail and guard rules apply.
It depends on the finished floor-to-floor height, including the floor framing. For a 108 inch rise you need 14 risers of about 7.71 inches and 13 treads.
Plan, form, pour, finish and cure a concrete patio. Real material numbers for a 12×12 slab, joint spacing, curing time and the mistakes that cause cracks.
Compare the real cost and effort of 80 lb bags against ready-mix delivery, including short-load fees, and find the size where a truck starts to make sense.
Typical concrete slab thickness for patios, walkways, shed bases, driveways and garages — and how going from 4 to 5 inches changes strength and cost.