Concrete Steps Calculator

Estimate concrete for solid poured steps and a top landing, like a front stoop or garage entry.

Enter your numbers

Count every rise, including the one up onto the landing.

ft
in
in
in

Set equal to the tread depth if there is no landing.

%

Results

How this calculator works

Solid steps are treated as a stack of blocks that each run down to the ground. The bottom step is one riser tall, the next is two risers tall, and so on; the top landing is the full height. Adding these blocks gives the total volume.

Steps (k = 1 … n−1) = Width × Tread × Riser × (n−1)·n ÷ 2 Landing = Width × Landing depth × n × Riser Total = (Steps + Landing) × (1 + Waste%/100)

Assumptions and tips

  • Bag yields follow the manufacturer’s published figures: 80 lb ≈ 0.60 cu ft, 60 lb ≈ 0.45 cu ft, 50 lb ≈ 0.375 cu ft, 40 lb ≈ 0.30 cu ft.
  • Bag counts are always rounded up to whole bags.
  • The waste allowance covers spillage, uneven subgrade and over-excavation. 5–10% is common; use more for irregular forms.
  • Assumes solid steps. Steps poured over fill or against a wall use less concrete.

Worked example

Using the default values in the calculator above:

InputValue
Number of risers3
Step width4 ft
Riser height7 in
Tread depth11 in
Top landing depth36 in
Waste allowance10 %
Bag size80 lb bag (0.60 cu ft)

ResultValue
Concrete needed1.12 cubic yards
80 lb bags51 bags
Volume (with waste)30.2 cu ft
Total height21 in
Total run including landing58 in

Step by step:

  1. Steps below the landing: 4 × 0.917 × 0.583 × (2×3÷2) = 6.42 cu ft
  2. Landing: 4 × 3 × 3 × 0.583 = 21 cu ft
  3. Total with 10% waste = 30.16 cu ft = 1.117 yd³
  4. Bags = 30.16 ÷ 0.6 → 51

Concrete for typical entry steps

4 ft wide, 7 in risers, 11 in treads, 10% waste.

Risers & landing depthConcrete needed80 lb bags
2 risers, 36 in landing0.66 cubic yards30 bags
3 risers, 36 in landing1.12 cubic yards51 bags
4 risers, 36 in landing1.66 cubic yards75 bags
3 risers, no landing0.52 cubic yards24 bags

Common mistakes to avoid

  • Counting treads instead of risers — the landing step counts as a riser.
  • Pouring solid when fill would do: big landings use most of the concrete.

Frequently asked questions

How many bags of concrete for 3 steps?

With the defaults (4 ft wide, 7 in risers, 11 in treads and a 36 in deep landing) you need about 1.1 cubic yards — 51 bags of 80 lb mix with 10% waste. Most of that is the landing; a shallower landing needs much less.

Can I reduce the concrete needed?

Yes. Builders often fill the core with compacted gravel or rubble, which can cut the concrete substantially. Subtract the fill volume from the result.

Sources

Last reviewed: 2026-10-20 · How we build and check calculators